The heaviest domain on the exam (about 20%) and the most calculation-driven. It tests whether you can read contractor financial statements, run job costs, recognize revenue on long jobs, and compute the ratios sureties use to size your bonding capacity.

What the exam asks

  • Percentage-of-completion math: percent complete, revenue earned, and whether a job is over- or underbilled.
  • Ratios read off a balance sheet: current, quick, working capital and debt-to-equity.
  • Depreciation by straight-line, double-declining balance and units of production.
  • Job-cost arithmetic: labor burden, equipment ownership cost, and the cost of skipping a supplier discount.

Part 1 of 5

How the books are kept

Before any arithmetic, know which set of rules the numbers follow: when revenue counts, which costs belong to a job, and how inventory and supplier terms are handled.

Cash or accrual, completed-contract or percentage-of-completion

Cash-basis books record money when it moves; accrual books record revenue when earned and expenses when incurred, which is what financial statements and sureties expect. For long-term contracts, percentage-of-completion recognizes revenue as the work is done (cost-to-cost is the usual measure) and gives a steady income picture; completed-contract defers everything until the job closes and is used for short jobs or where estimates are unreliable. A projected loss on any contract is recognized in full as soon as it is known under either method.

Direct costs vs overhead

Direct costs trace to one job (materials, job labor, subs). General overhead (office rent, estimator salaries) must be recovered through markup — and markup on cost is not the same as margin on price.

Inventory and payables are tested as math

FIFO charges the oldest costs to jobs first (higher inventory and profit when prices rise). Supplier terms of 2/10, net 30 are worth about 37% a year — borrow to take the discount. Bank reconciliations add deposits in transit and subtract outstanding checks from the bank balance.

Work it: Cost of skipping a cash discount

Annual cost = Discount ÷ (100 − Discount) × 365 ÷ Days paid early

%
days
days

Days paid early to earn the discount

30 days − 10 days equals 20 days

Annualized cost of paying late instead

2% ÷ (100 − 2%) × 365 ÷ days early equals 37.2%

Worked example

Fig — Margin vs. markup — the costliest mix-up
  1. Markup
    Price = cost × (1 + markup) → $80,000 × 1.20 = $96,000

    Markup is a percentage of COST.

  2. Margin
    Price = cost ÷ (1 − margin) → $80,000 ÷ 0.80 = $100,000

    Margin is a percentage of PRICE.

  3. The trap
    A 20% markup is only a 16.7% margin

    Bid with the wrong one and the difference comes straight out of profit.

Part 2 of 5

What a job really costs: labor, equipment, depreciation

The wage and the purchase price are only the start. Burden rides on every labor hour, and a machine costs money every hour of its life whether it is working or parked.

Labor costs more than the wage

Labor burden is everything the employer pays on top of wages — FICA, FUTA/SUTA, workers' compensation, liability insurance tied to payroll, health and retirement benefits, paid time off — expressed as a percentage of wages and added to every labor hour in an estimate. A crew estimated at bare wages is underpriced by the burden, which in construction is commonly 30 to 45 percent.

Work it: Labor burden

Burden rate = Burden per hour ÷ Wage

$
$

Burden rate

$7 ÷ $20 equals 35%

Loaded labor cost per hour

$20 + $7 equals $27.00

What one labor hour costs$27

  • Wage
  • Burden

Equipment: ownership costs run whether it works or not

Ownership cost is the purchase price less salvage, plus interest, insurance, taxes and storage, spread over the machine's expected life in hours. Operating cost — fuel, lubricants, tires, repairs, operator — accrues only when it runs. Jobs are charged an hourly rate that recovers both, and the comparison with a rental rate decides whether to own. Depreciation on the books (straight-line, declining balance, units of production) is the accounting version of the same idea: allocating cost over useful life, never a statement of market value.

Work it: Hourly ownership cost

Ownership per hour = (Price − Salvage) ÷ Life in hours

$
$
hours

Depreciation share of the hourly rate (interest, insurance, taxes and storage are added on top)

($90,000 − $10,000) ÷ 8,000 hours equals $10.00

Depreciation is allocation, not valuation

Straight-line spreads (cost − salvage) evenly; double-declining balance applies twice the straight-line rate to book value; units-of-production charges (cost − salvage) per hour of use. Section 179 expenses the cost in year one for tax.

Work it: Depreciation, year one

Straight-line = (Cost − Salvage) ÷ Life. Double-declining = Book value × 2 ÷ Life.

$
$
years

Straight-line, every year

($60,000 − $10,000) ÷ 5 years equals $10,000

Double-declining, first year (salvage is not subtracted)

$60,000 × 2 ÷ 5 years equals $24,000

In your books: The Builder's Guide to Accounting works an equipment ownership-cost example in its equipment chapter. Tab it.

Part 3 of 5

Revenue on long jobs: percentage of completion and the WIP schedule

This is the most tested calculation in the domain. Three numbers go in (contract price, estimated cost, cost to date) and the billing position falls out.

Percentage-of-completion is the contractor method

Long-term jobs recognize revenue as costs are incurred, not as bills go out. The share of the estimated cost spent so far is the percent complete, and that share of the contract price is the revenue earned. Billings are tracked separately, and the gap between billings and earned revenue is over- or underbilling.

Work it: Percentage of completion

Percent complete = Cost to date ÷ Estimated total cost. Revenue earned = Percent complete × Contract price.

$
$
$

Percent complete

$200,000 ÷ $400,000 equals 50%

Revenue earned to date

Percent complete × $500,000 equals $250,000

Overbilled is a liability, underbilled is an asset

Billings in excess of costs and estimated earnings = liability (you owe work). Costs in excess of billings = asset (you're financing the owner). The WIP schedule lays this out job by job.

Work it: Over- or underbilled

Billing position = Billed to date − Revenue earned

$
$

Above zero is overbilled (a liability). Below zero is underbilled (an asset).

$280,000 − $250,000 equals $30,000

The WIP schedule is the surety's lie detector

For every open job: contract price, estimated cost, cost to date, percent complete (cost to date ÷ estimated cost), earned revenue (percent complete × contract price), and billings to date. Billings above earned revenue are overbillings — a liability, cash you hold for work not yet done; billings below earned are underbillings — an asset, but a surety reads large underbillings as unapproved change orders or cost overruns. When the estimated cost at completion rises job after job, that is profit fade, and it is the first thing a bonding agent asks about.

In your books: The percentage-of-completion chapter of the Builder's Guide to Accounting has a worked WIP schedule with the over- and underbilling accounts. Tab that page.

Part 4 of 5

Ratios the surety reads

Each ratio answers one question about the company. Learn the question along with the formula and the inverted-ratio distractors stop working on you.

Three ratios rule

Current ratio, quick ratio and working capital all compare current assets with current liabilities. The quick ratio leaves inventory out. Sureties read these three before writing your bonds.

Work it: Current ratio, quick ratio, working capital

Current ratio = Current assets ÷ Current liabilities

$
$
$
$

Current ratio (all current assets)

($100,000 + $300,000 + $100,000) ÷ $250,000 equals 2.00

Quick ratio (inventory left out)

($100,000 + $300,000) ÷ $250,000 equals 1.60

Working capital

Current assets − $250,000 equals $250,000

Ratios: what each one answers

Current ratio (current assets ÷ current liabilities) and quick ratio (cash + receivables ÷ current liabilities) answer 'can you pay this year's bills'; working capital is the dollar version and drives bonding capacity. Debt-to-equity answers 'who owns the company — you or the bank'. Gross profit percentage answers 'are jobs priced right', return on equity 'is the business worth the risk', and times interest earned 'can operating profit cover the interest'.

In your books: Tab the ratio formula pages. Checking a formula takes 20 seconds, and the wrong answers are built from skipped steps and inverted ratios.

Part 5 of 5

Cash runs on a different calendar

Profit on paper does not pay suppliers. The last part of the lesson is about when money actually arrives and how long it stays out.

Cash moves on a different calendar than profit

A profitable contractor can run out of cash: retainage (often 10 percent) is held until completion, pay applications are cut off on a date and paid 30 or more days later, and suppliers want payment in 30. The cash-flow projection lines up billings, expected collections and payables month by month; the schedule of values decides how fast a job bills (front-loading early line items is common and watched); the accounts-receivable aging and average collection period show how long the money is out.

Work it: Average collection period

Days outstanding = Receivables ÷ (Annual credit sales ÷ 365)

$
$

Credit sales per day

$1,825,000 ÷ 365 equals $5,000

Average collection period

$150,000 ÷ sales per day equals 30 days

Know these cold

The short list to have in your head on exam day. Every line is also a card in your flashcards.

Cash discount 2/10, net 30
≈ 37% annualized cost of skipping it
Double-declining rate
2 × (100% ÷ useful life), applied to book value
Anticipated contract loss
Recognize the whole loss as soon as it is known
% complete (cost-to-cost)
Costs to date ÷ total estimated costs
Quick ratio
(Current assets − inventory) ÷ current liabilities
Working capital
Current assets − current liabilities
Price for target margin
Cost ÷ (1 − margin) — not cost × (1 + margin)
Break-even revenue
Fixed costs ÷ contribution margin %
Straight-line depreciation
(Cost − salvage) ÷ useful life
Overbilling
Billings to date > earned revenue → a current LIABILITY (billings in excess of costs and estimated earnings).
Underbilling
Earned revenue > billings to date → a current ASSET (costs and estimated earnings in excess of billings); sureties distrust large ones.
Profit fade
Estimated gross profit on a job shrinking as it progresses — the surety's warning sign.
Labor burden
Employer taxes, workers' comp, insurance and benefits ÷ wages; added to every estimated labor hour.
Hourly ownership cost
(Cost − salvage) ÷ life hours, plus interest, insurance, taxes and storage per hour; operating cost is separate.
Average collection period
Accounts receivable ÷ (annual credit sales ÷ 365) = days the money is out.
Debt-to-equity
Total liabilities ÷ owner's equity — leverage the surety caps.
Gross profit percentage
(Revenue − direct job costs) ÷ revenue.
Return on equity
Net income ÷ owner's equity.
Times interest earned
Operating income (EBIT) ÷ interest expense.
Cost of skipping 2/10, net 30
Paying on day 30 instead of 10 costs 2% for 20 days — about 37% a year.
Loss contract
The whole projected loss is booked as soon as it is known, under either revenue method.

Where it lives in your books

The real exam is open book. Knowing which book and which tab answer this topic is worth as much as memorizing it.

Reading isn't learning. Retrieval is.

96 questions in this domain, each with an explanation and source.