Florida Lien Law
16% of this examFlorida's Construction Lien Law (FS 713) gives everyone who improves real property a path to payment security — if they hit every deadline. The official outline doesn't give lien law its own area (it runs through several), but it's among the most lookup-friendly topics on the exam: nearly every question turns on a deadline or a document name.
What the exam asks
- Who has lien rights and who does not, including the supplier to a supplier and the unlicensed contractor.
- The document chain: Notice of Commencement, Notice to Owner, Claim of Lien, suit to enforce, and which clock each one runs on.
- Counting 45 and 90 days from first or final furnishing, and spotting the trap dates.
- Waivers, proper payments and the final payment affidavit, and when an owner pays twice.
- Bonded jobs, ways to shorten or clear a lien, and the penalties for false documents.
Part 1 of 4
Who has lien rights
A lien is a claim against the property, not against the owner personally. Most exam questions start by asking whether the person even has a right to lien. A few side rules then decide what the lien reaches and how a lienor can lose it.
Who has lien rights
A lien is a claim against the improved property, enforced by foreclosure; it is not a personal claim against the owner. Rights run to the contractor, subcontractors, sub-subcontractors, laborers, material suppliers to any of those, and licensed design professionals. They stop there: a supplier to another supplier has none. Public property cannot be liened, which is why public jobs carry a section 255.05 bond. On a job of $2,500 or less only the contractor in privity with the owner can lien. An unlicensed contractor has no lien rights.
Other rules that get tested
Either side may demand a sworn statement of account; a lienor that does not answer within 30 days, or answers falsely, loses its lien. A lien for a tenant's improvements normally reaches only the leasehold. When one spouse contracts for work on jointly owned property, the other is deemed to consent unless he or she objects in writing within 10 days of learning of it. Residential direct contracts over $2,500 must carry the statutory lien-law warning to the owner. An unpaid supplier may take back delivered materials that have not been built in. Delivery to the site is prima facie evidence the materials went into the job.
In your books: If the question asks who must serve rather than when, start at the definitions in 713.01. Privity decides the answer.
Part 2 of 4
The document chain and its deadlines
Each document has its own trigger and its own clock. Most wrong answers use the right number counted from the wrong event, so learn which event starts which clock.
The document chain follows the project
Owner records a Notice of Commencement before work starts. Lienors without a direct owner contract serve a Notice to Owner within 45 days of first furnishing. Anyone unpaid records a Claim of Lien within 90 days of final furnishing, serves it on the owner within 15 days, and must sue within 1 year.
Priority, expiration, and termination of the Notice of Commencement
With a recorded Notice of Commencement, every lien relates back to the day it was recorded, which is why a lender records its mortgage first. Without one, each lien takes priority only from the day its own claim is recorded. The notice names the owner, contractor, surety and bond amount, and lender, and is posted on site. It lasts one year unless it states another date; work after it expires is treated as if no notice were in effect. A Notice of Termination takes effect no sooner than 30 days after recording and goes with the contractor's final payment affidavit.
The Notice to Owner in detail
The Notice to Owner is served, not recorded, and puts nothing on the title. Laborers do not have to serve one; every other lienor without a direct contract with the owner does. The 45 days is an outside limit: the notice must also arrive before the owner makes final payment on the contractor's final payment affidavit. A sub-subcontractor or a supplier to a subcontractor also serves a copy on the contractor. Certified mail is effective on the date of mailing if it is mailed within 40 days of first furnishing to the address in the Notice of Commencement.
Counting the days
Count calendar days from the day after the event. First furnishing March 2: 29 days left in March plus 16 in April puts the 45th day on April 16. Final furnishing April 4: 26 days left in April, 31 in May, 30 in June makes 87, so the 90th day is July 3. Final furnishing is the last day of contract work or the last delivery. Punch-list touch-ups, warranty repairs, the invoice date, and the payment due date do not move it.
What goes in a claim of lien
The claim is sworn. It states the lienor's name and address, who the lienor contracted with, what was furnished and the contract price or value, the property description, the amount unpaid, and the dates of first and last furnishing. One claim covers everything furnished under one direct contract. It can be amended within the original 90 days. A good-faith error does not defeat it unless someone was harmed, but a willfully exaggerated claim is a fraudulent lien: a complete defense for the owner, damages and attorney's fees against the lienor, and a third-degree felony.
Worked examples
- StartNotice of Commencement
Recorded by the owner before work begins; expires in 1 year unless a longer period is stated.
- Day 0First furnishing
The lienor's first day of labor or materials on the job.
- +45 daysNotice to Owner served
Within 45 days of FIRST furnishing, for lienors not in privity with the owner. Missing it is a complete defense.
- Final dayFinal furnishing
The lienor's last day of labor, services, or materials.
- +90 daysClaim of lien recorded
Within 90 days of FINAL furnishing — and a copy served on the owner within 15 days of recording.
- +1 yearSuit to enforce
Within 1 year of recording — shortened to 60 days if the owner serves a Notice of Contest of Lien.
- First furnishingMarch 2
- Days left in March31 − 2 = 29 days (through March 31)
- Days needed in April45 − 29 = 16
The day of first furnishing is not counted.
- DeadlineApril 16
- Final furnishingApril 4
- April, May, June26 + 31 + 30 = 87 days (through June 30)
- Days needed in July90 − 87 = 3
- DeadlineJuly 3
May 19 is the 45-day mark, the trap answer.
In your books: Every deadline lives in four sections: 713.06 (Notice to Owner), 713.08 (claim of lien), 713.13 (Notice of Commencement) and 713.21 and 713.22 (duration). Tab all four.
Part 3 of 4
Paying safely and signing waivers
An owner who follows the payment steps never pays more than the contract price. An owner who skips them can pay twice. Waivers are statutory forms, and what they cover is narrower than most people assume.
Proper payments keep the owner from paying twice
An owner who follows the statute never pays more than the contract price. At each progress payment the owner may require lien releases from everyone who served a Notice to Owner and may pay them directly or by joint check. Final payment is proper only after the contractor's final payment affidavit, which says everyone is paid or lists who is not and how much. Payments made while ignoring served notices are improper and do not reduce what the owner owes lienors.
The owner has defenses
An owner who follows the 'proper payments' procedure (getting releases and the contractor's final payment affidavit before paying) cannot be forced to pay twice. A missed NTO or late claim of lien is a complete or partial defense.
Waivers are forms, not promises
FS 713.20 supplies two statutory forms: a waiver and release upon progress payment (covers work through a stated date, not retention or later work) and one upon final payment. Lien rights can't be waived in advance, and a waiver given for a check can be conditioned on that check clearing.
Part 4 of 4
Bonds, clearing a lien, and the penalties
A bond swaps the property for a different target and a different clock. An owner also has ways to shorten or clear a lien. The law backs all of it with felony penalties for false papers and misused money.
Bonds replace liens
When a payment bond under 713.23 covers the project, the property is exempt from most liens — subs and suppliers claim against the bond instead.
Bonded jobs have their own clock
With a 713.23 payment bond (or a 255.05 public bond) the lienor serves a notice to contractor within 45 days of first furnishing and a sworn notice of nonpayment within 90 days after final furnishing, then sues the surety within 1 year of final furnishing.
How an owner clears or shortens a lien
A Notice of Contest of Lien, recorded and served by the clerk, cuts the lienor's time to sue from one year to 60 days. A summons to show cause gives the lienor 20 days. Any interested party can transfer the lien to a bond or cash deposit with the clerk, in the amount of the lien plus three years' interest plus the greater of $1,000 or 25% of the lien amount for costs, and the lien then attaches to that security and not the land. A lien also dies by satisfaction, by court order, or by the year running out with no suit. The prevailing party in a lien action recovers attorney's fees.
The lien law has criminal teeth
Misapplying construction funds (713.345) is a felony graded by amount, and knowingly signing a false final affidavit or waiver (713.35) is a third-degree felony.
Worked examples
- Day 0First furnishing
- +45 daysNotice to contractor
From a lienor not in privity with the contractor: it will look to the bond
- Final dayFinal furnishing
- +90 daysSworn notice of nonpayment
Served on the contractor and the surety, counted from final furnishing
- +1 yearSuit on the bond
One year from final furnishing, not from recording
- Day 0Claim of lien recorded
Enforceable for 1 year by default.
- Owner actsNotice of Contest of Lien served
A low-cost tool that forces the lienor's hand.
- +60 daysSuit deadline
Sue within 60 days of service or the lien is extinguished.
- After a show-cause summons20 days
- After a Notice of Contest of Lien60 days
- Default: one year from recording365 days
Know these cold
The short list to have in your head on exam day. Every line is also a card in your flashcards.
- Notice of Commencement threshold
- Direct contract over $2,500; recorded before work starts, certified copy posted on site — 713.13
- Notice of nonpayment (bonded job)
- Within 90 days after final furnishing, under oath — 713.23(1)(d)
- Lender stopping advances
- Notice to the contractor within 5 business days — 713.3471
- Notice to Owner
- Serve within 45 days of first furnishing (FS 713.06)
- Claim of Lien
- Record within 90 days of final furnishing (FS 713.08); serve on owner within 15 days
- Enforcement window
- 1 year from recording — shortened to 60 days by a Notice of Contest (FS 713.22)
- Final payment affidavit
- Give owner at least 5 days before suing on the lien (FS 713.06(3)(d))
- Notice of Commencement
- Effective 1 year by default (FS 713.13)
- Farthest lienor
- Supplier to a sub-subcontractor; a supplier to a supplier has no rights — FS 713.01
- Laborers
- No Notice to Owner required — FS 713.06(2)
- Notice to Owner outer limit
- 45 days from first furnishing AND before final payment on the contractor's affidavit
- Certified mail
- Effective on mailing if mailed within 40 days of first furnishing — FS 713.18(3)
- Final furnishing
- Last contract work or delivery; not punch list, warranty, or invoice date
- Amending a claim of lien
- Within the 90 days allowed to record the original — FS 713.08(4)(b)
- Fraudulent lien
- Willful exaggeration: lien lost, damages and fees, third-degree felony — FS 713.31
- Show-cause summons
- Lienor has 20 days to respond — FS 713.21
- Transfer to bond
- Lien amount + 3 years' interest + greater of $1,000 or 25% of the lien — FS 713.24
- Sworn statement of account
- Answer within 30 days of written demand or lose the lien — FS 713.16
- Lien priority
- Relates back to the recording of the Notice of Commencement — FS 713.07(2)
- Notice of Termination
- Effective no sooner than 30 days after recording — FS 713.132
- Advance waiver
- Unenforceable; rights are waived only as work is paid for — FS 713.20
- Spouse's objection
- Written notice within 10 days of learning of the contract — FS 713.12
- Attorney's fees
- Awarded to the prevailing party in a lien action — FS 713.29
- Jobs of $2,500 or less
- Only the contractor in privity may lien — FS 713.02(5)
Where it lives in your books
The real exam is open book. Knowing which book and which tab answer this topic is worth as much as memorizing it.
- Lien Law (FS 713) · 9 recommended tabsLien questions are deadline questions. Tab the deadline sections and answer from the statute, not from memory — one wrong number is the difference between a right and wrong answer.
- Contractor's Manual · 8 recommended tabsThis is your home base on exam day. Learn its table of contents — most candidates lose time flipping because they never learned which chapter holds which statute.
Reading isn't learning. Retrieval is.
77 questions in this domain, each with an explanation and source.