Skip to content

Changes, Claims & Disputes

12% of this exam

The A201 machinery for changes and disputes: change orders vs construction change directives, the 21-day claims clock, differing site conditions, and the mediation-first resolution ladder. This is the most A201-citation-heavy domain — almost every answer is in Article 7 or Article 15.

What the exam asks

  • Change order versus construction change directive: who signs, and who must proceed.
  • The A201 claim sequence: 21-day written notice, Initial Decision Maker, mediation, then arbitration or litigation.
  • Differing site conditions, Type I and Type II, and giving notice before a concealed condition is disturbed.
  • Sorting a delay into excusable and compensable, excusable only, or non-excusable.
  • Arithmetic: pricing a change with overhead and profit, and liquidated damages as days times the daily rate.

Part 1 of 4

Changing the work

Most extra work starts with a change order or a directive. Know who signs each one, how the change gets priced, and what happens when the work changes with no paper at all.

Change order vs CCD

A change order is signed by all three parties — owner, contractor, and architect — and adjusts scope, sum, or time by agreement. A construction change directive (CCD) is signed by only the owner and architect and orders the work to proceed before price or time is agreed; once agreement is reached it becomes a change order. The contractor must proceed under a CCD.

Pricing the change and the owner's self-help

Change order pricing itemizes burdened labor, material, equipment, and affected subcontract costs, then adds the overhead and profit percentage the contract allows: $14,200 + $9,800 = $24,000 of direct cost, 15% is $3,600, and the change is $27,600. If the contractor neglects the work and does not correct it within the notice period, A201 lets the owner correct it and deduct the reasonable cost.

Work it: Pricing a change order

Change order = Direct cost + (Direct cost × Overhead and profit %)

$
$
%

Direct cost

$14,200 + $9,800 equals $24,000

Overhead and profit

15%% × direct cost equals $3,600

Change order amount

Direct cost + overhead and profit equals $27,600

What the change order adds up to$27,600

  • Direct cost
  • Overhead and profit

Constructive change, cardinal change, constructive acceleration

A constructive change is owner or architect conduct that changes the work with no written change order: demanding more than the contract requires, misreading the specifications, rejecting conforming work. Give written notice and claim it. A cardinal change is so far outside the original bargain that the changes clause does not reach it, and the contractor may treat the direction as a breach. Constructive acceleration has five parts: the contractor was entitled to a time extension, asked for it properly, was refused, was held to the original date, and actually accelerated at added cost.

In your books: Tab A201 Article 7. It holds the change order and CCD signature rules.

Part 2 of 4

Claims and the resolution ladder

A claim has a clock and an order of steps. Miss the 21-day notice and you can lose the claim. Skip mediation and the arbitration demand is premature.

Claims have a 21-day fuse

Under A201 Article 15, a claim must be initiated by written notice within 21 days after the event (or after the claimant first recognizes the condition, whichever is later). Late notice can waive the claim. The Initial Decision Maker — the architect, unless someone else is named — rules first; mediation is then a condition precedent to arbitration or litigation.

Keep working, keep getting paid

While a claim is pending, A201 requires the contractor to proceed diligently with the work and the owner to keep paying the amounts not in dispute. Walking off over a disputed claim risks a default. A signed change order is the full agreement on both money and time for that change, so one that reads 'no change' to the contract time is routinely treated as a waiver of schedule impact.

Worked examples

Fig — The A201 claim sequence
  1. EventThe event occurs, or the claimant first recognizes the condition

    The clock starts from whichever is later

  2. +21 daysWritten notice of the claim is due

    Late notice can waive the claim

  3. NextInitial decision

    By the Initial Decision Maker: the architect unless another is named

  4. ThenMediation

    A condition precedent to binding dispute resolution

  5. LastArbitration or litigation

    Whichever the agreement selects

Fig — Claim notice date
  1. Event occurs
    March 1
  2. Condition first recognized
    March 15 (the later date controls)
  3. Notice due
    March 15 + 21 days = April 5

In your books: Tab A201 Article 15. It holds the 21 days, the Initial Decision Maker and the mediation-first rule.

Part 3 of 4

Site conditions you did not expect

Unknown conditions in the ground are a claim for time and money, but only if you tell the right people before you disturb them.

Differing site conditions come in two types

Type I: actual conditions differ materially from what the contract documents indicated (rock at 8 feet where borings showed sand). Type II: an unknown condition of an unusual nature for the area — no contract representation needed. Both can support a claim for time and money.

Concealed conditions: notice before you disturb it

The party that finds a concealed or unknown condition gives prompt notice before the condition is disturbed, so the architect can look at it and decide whether cost or time should change. Digging it out first destroys the proof. Notice is not a formality: it lets the owner inspect, track the cost as it is spent, or pick a cheaper fix.

In your books: Differing site conditions sit in A201 section 3.7.4. The Type I and Type II split turns on whether the contract documents represented the condition.

Part 4 of 4

Delay, damages and getting out of the contract

Sort the delay first, because the bin decides whether the contractor gets time, money, both or neither. Then see what the owner can collect and what happens when the owner suspends or terminates.

Sort the delay before you answer

Three bins. Owner-caused delay is excusable and compensable: time and money. Delay nobody caused (a hurricane, weather abnormal for the season) is excusable but not compensable: time only. Contractor-caused delay is non-excusable: no time, no money, and liquidated damages run. When owner and contractor delays hit the critical path over the same period, the usual rule is time but no money.

Weather only counts when it is abnormal

To earn a time extension, weather has to be abnormal for the period, not reasonably anticipated, and it has to actually affect the work. Ordinary seasonal weather is the contractor's risk and belongs in the baseline schedule.

Delay damages are fenced in

Liquidated damages are enforceable only as a reasonable pre-estimate of delay damages — never as a penalty. A201's mutual waiver of consequential damages bars the owner's lost rents and profits (and the contractor's home-office overhead), leaving liquidated damages as the delay remedy. A no-damages-for-delay clause limits the contractor to a time extension only.

Liquidated damages replace actual damages

LDs are days of unexcused delay times the daily rate: 12 days at $1,500 is $18,000. The owner does not have to prove its loss, and it cannot collect actual delay damages on top of, or instead of, the stipulated sum for the same delay. A201's mutual waiver of consequential damages does not block liquidated damages. Courts recognize narrow exceptions to a no-damages-for-delay clause, such as the owner's bad faith or active interference.

Work it: Liquidated damages

Liquidated damages = Days of unexcused delay × Daily rate

days
$

Liquidated damages owed to the owner

12 days × $1,500 equals $18,000

Suspension and termination for convenience

A201 lets the owner suspend the work without cause. Time is extended and the contract sum is adjusted for the added cost (demobilization and remobilization, idle equipment, extended general conditions), and A201 says that adjustment includes profit. Termination for convenience pays for the work executed with its overhead and profit, the costs caused by the termination, and any termination fee the agreement states. It does not pay anticipated profit on the work not performed.

In your books: Owner suspension of the work is in A201 Article 14.

Know these cold

The short list to have in your head on exam day. Every line is also a card in your flashcards.

Change order signatures
Owner + contractor + architect (A201 Art. 7)
CCD
Owner + architect only; work proceeds before price/time agreed (A201 Art. 7)
Claim notice
21 days from the event or recognition of the condition (A201 Art. 15)
Initial Decision Maker
The architect, unless the parties designate someone else (A201 Art. 15)
Before arbitration/litigation
Mediation is a condition precedent (A201 Art. 15)
Liquidated damages
Enforceable as a reasonable forecast of delay damages, not a penalty
Owner-caused delay
Excusable and compensable: time and money
Hurricane / abnormal weather
Excusable, not compensable: time only
Contractor-caused delay
Non-excusable: no time, no money
Concurrent delay
Time but no money
Constructive change
Owner or architect conduct changes the work without a written change order
Cardinal change
Beyond the general scope; may be treated as a breach
Constructive acceleration
Entitled to time, asked, refused, held to the date, accelerated at cost
Pending a claim
Contractor keeps working; owner keeps paying undisputed amounts — A201 Art. 15
Change order with no time
Treated as a waiver of schedule impact for that change
Liquidated damages math
Days of unexcused delay × the daily rate; no proof of actual loss
LDs and actual damages
The stipulated sum replaces actual delay damages; not both
Owner suspension
Time extended and cost adjusted, including profit — A201 Art. 14
Termination for convenience
Work done, termination costs, any stated fee; no profit on unperformed work
Concealed condition
Prompt notice before it is disturbed — A201 §3.7.4

Where it lives in your books

The real exam is open book. Knowing which book and which tab answer this topic is worth as much as memorizing it.

Reading isn't learning. Retrieval is.

35 questions in this domain, each with an explanation and source.