Changes, Claims & Disputes
12% of this examThe A201 machinery for changes and disputes: change orders vs construction change directives, the 21-day claims clock, differing site conditions, and the mediation-first resolution ladder. This is the most A201-citation-heavy domain — almost every answer is in Article 7 or Article 15.
What the exam asks
- Change order versus construction change directive: who signs, and who must proceed.
- The A201 claim sequence: 21-day written notice, Initial Decision Maker, mediation, then arbitration or litigation.
- Differing site conditions, Type I and Type II, and giving notice before a concealed condition is disturbed.
- Sorting a delay into excusable and compensable, excusable only, or non-excusable.
- Arithmetic: pricing a change with overhead and profit, and liquidated damages as days times the daily rate.
Part 1 of 4
Changing the work
Most extra work starts with a change order or a directive. Know who signs each one, how the change gets priced, and what happens when the work changes with no paper at all.
Change order vs CCD
A change order is signed by all three parties — owner, contractor, and architect — and adjusts scope, sum, or time by agreement. A construction change directive (CCD) is signed by only the owner and architect and orders the work to proceed before price or time is agreed; once agreement is reached it becomes a change order. The contractor must proceed under a CCD.
Pricing the change and the owner's self-help
Change order pricing itemizes burdened labor, material, equipment, and affected subcontract costs, then adds the overhead and profit percentage the contract allows: $14,200 + $9,800 = $24,000 of direct cost, 15% is $3,600, and the change is $27,600. If the contractor neglects the work and does not correct it within the notice period, A201 lets the owner correct it and deduct the reasonable cost.
Change order = Direct cost + (Direct cost × Overhead and profit %)
Direct cost
$14,200 + $9,800 equals $24,000
Overhead and profit
15%% × direct cost equals $3,600
Change order amount
Direct cost + overhead and profit equals $27,600
What the change order adds up to$27,600
- Direct cost
- Overhead and profit
Constructive change, cardinal change, constructive acceleration
A constructive change is owner or architect conduct that changes the work with no written change order: demanding more than the contract requires, misreading the specifications, rejecting conforming work. Give written notice and claim it. A cardinal change is so far outside the original bargain that the changes clause does not reach it, and the contractor may treat the direction as a breach. Constructive acceleration has five parts: the contractor was entitled to a time extension, asked for it properly, was refused, was held to the original date, and actually accelerated at added cost.
In your books: Tab A201 Article 7. It holds the change order and CCD signature rules.
Part 2 of 4
Claims and the resolution ladder
A claim has a clock and an order of steps. Miss the 21-day notice and you can lose the claim. Skip mediation and the arbitration demand is premature.
Claims have a 21-day fuse
Under A201 Article 15, a claim must be initiated by written notice within 21 days after the event (or after the claimant first recognizes the condition, whichever is later). Late notice can waive the claim. The Initial Decision Maker — the architect, unless someone else is named — rules first; mediation is then a condition precedent to arbitration or litigation.
Keep working, keep getting paid
While a claim is pending, A201 requires the contractor to proceed diligently with the work and the owner to keep paying the amounts not in dispute. Walking off over a disputed claim risks a default. A signed change order is the full agreement on both money and time for that change, so one that reads 'no change' to the contract time is routinely treated as a waiver of schedule impact.
Worked examples
- EventThe event occurs, or the claimant first recognizes the condition
The clock starts from whichever is later
- +21 daysWritten notice of the claim is due
Late notice can waive the claim
- NextInitial decision
By the Initial Decision Maker: the architect unless another is named
- ThenMediation
A condition precedent to binding dispute resolution
- LastArbitration or litigation
Whichever the agreement selects
- Event occursMarch 1
- Condition first recognizedMarch 15 (the later date controls)
- Notice dueMarch 15 + 21 days = April 5
In your books: Tab A201 Article 15. It holds the 21 days, the Initial Decision Maker and the mediation-first rule.
Part 3 of 4
Site conditions you did not expect
Unknown conditions in the ground are a claim for time and money, but only if you tell the right people before you disturb them.
Differing site conditions come in two types
Type I: actual conditions differ materially from what the contract documents indicated (rock at 8 feet where borings showed sand). Type II: an unknown condition of an unusual nature for the area — no contract representation needed. Both can support a claim for time and money.
Concealed conditions: notice before you disturb it
The party that finds a concealed or unknown condition gives prompt notice before the condition is disturbed, so the architect can look at it and decide whether cost or time should change. Digging it out first destroys the proof. Notice is not a formality: it lets the owner inspect, track the cost as it is spent, or pick a cheaper fix.
In your books: Differing site conditions sit in A201 section 3.7.4. The Type I and Type II split turns on whether the contract documents represented the condition.
Part 4 of 4
Delay, damages and getting out of the contract
Sort the delay first, because the bin decides whether the contractor gets time, money, both or neither. Then see what the owner can collect and what happens when the owner suspends or terminates.
Sort the delay before you answer
Three bins. Owner-caused delay is excusable and compensable: time and money. Delay nobody caused (a hurricane, weather abnormal for the season) is excusable but not compensable: time only. Contractor-caused delay is non-excusable: no time, no money, and liquidated damages run. When owner and contractor delays hit the critical path over the same period, the usual rule is time but no money.
Weather only counts when it is abnormal
To earn a time extension, weather has to be abnormal for the period, not reasonably anticipated, and it has to actually affect the work. Ordinary seasonal weather is the contractor's risk and belongs in the baseline schedule.
Delay damages are fenced in
Liquidated damages are enforceable only as a reasonable pre-estimate of delay damages — never as a penalty. A201's mutual waiver of consequential damages bars the owner's lost rents and profits (and the contractor's home-office overhead), leaving liquidated damages as the delay remedy. A no-damages-for-delay clause limits the contractor to a time extension only.
Liquidated damages replace actual damages
LDs are days of unexcused delay times the daily rate: 12 days at $1,500 is $18,000. The owner does not have to prove its loss, and it cannot collect actual delay damages on top of, or instead of, the stipulated sum for the same delay. A201's mutual waiver of consequential damages does not block liquidated damages. Courts recognize narrow exceptions to a no-damages-for-delay clause, such as the owner's bad faith or active interference.
Liquidated damages = Days of unexcused delay × Daily rate
Liquidated damages owed to the owner
12 days × $1,500 equals $18,000
Suspension and termination for convenience
A201 lets the owner suspend the work without cause. Time is extended and the contract sum is adjusted for the added cost (demobilization and remobilization, idle equipment, extended general conditions), and A201 says that adjustment includes profit. Termination for convenience pays for the work executed with its overhead and profit, the costs caused by the termination, and any termination fee the agreement states. It does not pay anticipated profit on the work not performed.
In your books: Owner suspension of the work is in A201 Article 14.
Know these cold
The short list to have in your head on exam day. Every line is also a card in your flashcards.
- Change order signatures
- Owner + contractor + architect (A201 Art. 7)
- CCD
- Owner + architect only; work proceeds before price/time agreed (A201 Art. 7)
- Claim notice
- 21 days from the event or recognition of the condition (A201 Art. 15)
- Initial Decision Maker
- The architect, unless the parties designate someone else (A201 Art. 15)
- Before arbitration/litigation
- Mediation is a condition precedent (A201 Art. 15)
- Liquidated damages
- Enforceable as a reasonable forecast of delay damages, not a penalty
- Owner-caused delay
- Excusable and compensable: time and money
- Hurricane / abnormal weather
- Excusable, not compensable: time only
- Contractor-caused delay
- Non-excusable: no time, no money
- Concurrent delay
- Time but no money
- Constructive change
- Owner or architect conduct changes the work without a written change order
- Cardinal change
- Beyond the general scope; may be treated as a breach
- Constructive acceleration
- Entitled to time, asked, refused, held to the date, accelerated at cost
- Pending a claim
- Contractor keeps working; owner keeps paying undisputed amounts — A201 Art. 15
- Change order with no time
- Treated as a waiver of schedule impact for that change
- Liquidated damages math
- Days of unexcused delay × the daily rate; no proof of actual loss
- LDs and actual damages
- The stipulated sum replaces actual delay damages; not both
- Owner suspension
- Time extended and cost adjusted, including profit — A201 Art. 14
- Termination for convenience
- Work done, termination costs, any stated fee; no profit on unperformed work
- Concealed condition
- Prompt notice before it is disturbed — A201 §3.7.4
Where it lives in your books
The real exam is open book. Knowing which book and which tab answer this topic is worth as much as memorizing it.
Reading isn't learning. Retrieval is.
35 questions in this domain, each with an explanation and source.