contract

AIA Contract Documents (A201 family)

The standard construction contract forms: A201 General Conditions plus the agreement forms (A101/A102/A133, A401 subcontract), bid documents (A310, A701), bonds (A312), and payment forms (G702/G703, G707).

54 questions in our bank cite this reference.

The one thing to know

A201 article numbers are the map: Art. 3 contractor, Art. 7 changes, Art. 8 time, Art. 9 payments, Art. 11 insurance, Art. 12 corrections, Art. 14 termination, Art. 15 claims. Most Contract Admin questions cite one of these.

Your tab set

Florida exams allow pre-tabbed, highlighted references. Build these tabs before exam day, in book order.

1
General provisionsA201 Art. 1

The contract documents, definitions, order of precedence

2
Contractor responsibilitiesA201 Art. 3

Supervision, submittals & shop drawings (3.11–3.12), concealed conditions (3.7.4), allowances (3.8), warranties

3
Changes in the workA201 Art. 7

Change orders vs construction change directives

4
Time & delaysA201 Art. 8

Contract time, delay causes, extensions of time

5
Payments & completionA201 Art. 9

Schedule of values (9.2), retainage, substantial completion (9.8), final payment (9.10), punch list

6
Insurance & bondsA201 Art. 11

Required coverage, waiver of subrogation

7
Correction of workA201 Art. 12

1-year correction period (12.2)

8
Termination & suspensionA201 Art. 14

For cause vs for convenience

9
Claims & disputesA201 Art. 15

21-day notice, initial decision maker, mediation before binding resolution

10
Agreement formsA101 / A102 / A133 / A401

Stipulated sum vs cost-plus-GMP vs CM as constructor; the subcontract form

11
Bidding documentsA701 / A310

Instructions to bidders, bid security, withdrawal and mistake rules

12
Bonds & payment formsA312 / G702–G703 / G707

Performance & payment bonds, application and certificate for payment, consent of surety

Highlight the question, underline the answer

Don't just tab your books — mark them as you practice. Every time a question sends you into a reference, leave a two-part mark behind: highlight the passage the question is about, and underline the exact words that answer it. Do this through your whole question bank and the book turns into a map of the tested material — so on exam day you recognize the spot, not just the section.

  1. 1

    Highlight what the question asks about

    When you look up a practice question, highlight the sentence or table the question turns on. That block is now a visual landmark you'll spot on a fast flip.

  2. 2

    Underline the exact answer

    Inside the highlight, underline the specific number, deadline, or phrase that is the answer — with a fine-tip pen. Highlight = the topic; underline = the fact.

  3. 3

    Color-code by what trips you up

    Use one highlighter color for deadlines and numbers, another for definitions, a third for the answers you got wrong twice. Your weak spots become the brightest marks in the book.

  4. 4

    Let your tabs and marks compound

    A tab gets you to the chapter; the highlight gets you to the paragraph; the underline gets you to the answer. Built up across a full question bank, that three-layer trail is the open-book skill the exam actually tests.

All marking must be done before you walk in — the rules allow pre-marked books but bar making any new marks (or bringing notes) during the exam.

Navigating under time pressure

  • Changes: change order (all three parties) vs CCD (owner + architect, work proceeds) is Article 7.
  • Payment mechanics — schedule of values, certificates, retainage, substantial completion — run through Article 9.
  • Claims have a 21-day notice rule and a mediation-first sequence in Article 15.
  • Know which agreement form is which: A101 stipulated sum, A102 cost-plus with GMP, A133 CM as constructor, A401 subcontract.