Estimating & Bid Pricing
15% of this examContent Area A of the Contract Administration outline: building the number before the bid. Quantity takeoff, material/labor/equipment costing, overhead, square-foot (systems) estimating, fixed versus variable costs, break-even, markup versus margin, financing the cash-flow gap, and the regulatory costs (impact fees, permits, stormwater, OSHA) that belong in the price. Mostly arithmetic with a few definitions.
What the exam asks
- Markup, margin and break-even arithmetic: price = cost ÷ (1 − margin), and break-even revenue = fixed costs ÷ contribution margin.
- Unit prices built from a crew's daily production, with every worker and the labor burden counted.
- Sorting a cost into direct cost, job overhead (general conditions) or home-office overhead.
- Which estimate fits the drawings in hand, and how to level subcontractor quotes before comparing them.
Part 1 of 4
Pick the estimate that fits the drawings
Every estimate starts with one question: how much design exists? The answer decides whether a quick area-based number is honest or whether the job needs a full takeoff.
Square-foot estimates and what they are for
Area × historical cost per square foot gives a feasibility number fast, and a wide one. It is replaced by a detailed takeoff when drawings exist. Estimating software speeds takeoff and applies the company's assemblies, but the estimator still verifies scope, scale, and addenda.
Budget = Area × Cost per square foot
Feasibility budget
24,000 SF × $95 equals $2,280,000
Match the estimate to the drawings you have
With little design information, an order-of-magnitude or square-foot estimate from historical costs is the right tool, and everyone understands the accuracy is rough. Precision improves as the design develops. By the time drawings are 90% through design development there is enough to do a real quantity takeoff, and that is what a guaranteed maximum price commitment requires.
Part 2 of 4
Price the work: quantities, labor and equipment
A detailed estimate is built from the bottom up. Count the work, work out what a crew and its machines cost per day, and divide by what they produce. That gives the unit price everything else rests on.
From takeoff to unit price
Takeoff converts drawings into quantities in the unit being priced (CY, SF, LF), with waste added where the material is cut. Labor is priced from crew production at the burdened wage. Equipment carries ownership plus operating cost per hour. Subcontractor quotes are leveled for inclusions before the low one is used. General conditions (job overhead) are priced per job, and home-office overhead is recovered through markup.
Labor: production rate, crew cost, burden
Labor is priced from what a crew produces in a day. Count every worker in the crew; pricing one of two is the standard trap. Labor is priced at the burdened rate, not the bare wage: FICA, unemployment taxes, workers' compensation, payroll-based liability insurance, and fringes ride on top of the base wage.
Crew-days = Quantity ÷ Daily production
Time for the crew
12,000 SF ÷ 800 SF equals 15.0 crew-days
Unit labor cost = Daily crew cost ÷ Daily production
Daily crew cost (every worker counted)
2 × $38 × 8 equals $608
Labor cost per SF
Daily crew cost ÷ 300 SF equals $2.03
Equipment: ownership plus operating
Ownership costs run whether or not the machine turns a wheel: depreciation, interest, taxes, insurance, storage. Operating costs occur only when it works: fuel, lubricants, filters, tires or tracks, wear parts, routine repairs. The hourly rate spreads ownership over the expected annual hours and adds the operating cost per hour. The operator is priced separately as burdened labor. Rented equipment is the rental rate plus mobilization.
Building a unit price
A unit price is material + labor + equipment for one unit of work. Multiply it by the takeoff quantity. Waste goes on the material quantity before pricing.
Unit price = Material + Labor + Equipment, each for one unit of work
Labor per LF
$120 ÷ 20 LF equals $6.00
Equipment per LF
$30 ÷ 20 LF equals $1.50
Unit price per LF
Material + labor + equipment equals $15.50
What one LF costs$15.50
- Material
- Labor
- Equipment
Order quantity = Net quantity × (1 + Waste)
Quantity to order
2,000 SF × (1 + 8%) equals 2,160 SF
In your books: Walker's is the takeoff and productivity reference, and it is a study-only book for this exam, so the conversions and crew outputs have to be in your head.
Part 3 of 4
Complete the cost: quotes, overhead and risk
Your own crews are only part of the number. Subcontractor quotes, the cost of running the job site, and the money set aside for what is not yet known all have to land in the estimate, each in the right place.
Leveling subcontractor quotes
Quotes rarely cover the same scope: one leaves out scaffolding, another the top-of-wall fire caulking. A scope sheet lists every required item against every quote so the gaps can be priced. Add the missing cost to the incomplete quote, then compare. The GC's bid has to cover the whole specified scope no matter what a sub excluded, so an unpriced hole comes straight out of the GC's pocket. The apparent low quote is often not the real low once the holes are filled.
Direct cost, job overhead, home-office overhead
Sort every cost into one of three bins. Direct costs are the labor, material, and equipment built into a specific work item (footing rebar, drywall, structural steel). Job overhead, also called general conditions, is what it takes to run this project without belonging to one item: the superintendent, field office, temporary power, dumpsters, cleanup, a night security guard. Home-office overhead (rent, office staff, principals) is not charged to a job at all; it is recovered through markup. Exam questions hand you a cost and ask which bin it goes in.
Risk and regulation in the price
Liquidated damages turn schedule risk into dollars per day; price the acceleration or a contingency, not the whole duration. The cash-flow gap (pay now, get paid in 30+ days less retainage) has a financing cost. Impact fees, permit fees, environmental permits and their controls, and OSHA compliance are project costs, not overhead.
Allowance, contingency, escalation
An allowance is a stated dollar amount for a KNOWN item whose selection is not made yet; the price adjusts up or down when the owner picks. A contingency is a reserve for the UNKNOWN: estimating variance, small scope gaps, risk nobody can assign to a line. Escalation prices work at the cost level expected when it will actually be bought, item by item. It matters for long jobs and volatile, unlocked materials like structural steel; it does not apply to a subcontract price already fixed by a signed agreement.
Part 4 of 4
Turn cost into a price
Cost is what the job takes to build. Price is what you bid. The gap between them has to carry the home office and the profit, and this is where the exam's arithmetic is concentrated.
Overhead, break-even, markup, and margin
Fixed costs continue with no work, and variable costs follow volume. Break-even is the revenue at which the contribution margin has paid for the fixed costs. Markup is figured on cost and margin on price, so the same percentage gives two different prices.
Break-even revenue = Fixed costs ÷ Contribution margin
Revenue needed to break even
$600,000 ÷ 20% equals $3,000,000
Markup is figured on cost. Margin is figured on price.
Price at 20% markup on cost
$400,000 × (1 + 20%) equals $480,000
Price at 20% margin on price
$400,000 ÷ (1 − 20%) equals $500,000
Markup on cost$480,000
Margin on price$500,000
- Cost
- Profit
Markup goes on the full cost
Markup applies to direct cost plus general conditions, not to direct cost alone. Marking up only the direct cost earns nothing on the job overhead. Where overhead and profit are separate percentages, apply them in sequence instead of adding them together.
Bid = (Direct cost + General conditions) × (1 + Markup)
Markup on direct cost only (the mistake)
$500,000 × (1 + 15%) + $40,000 equals $615,000
Markup on the full cost
($500,000 + $40,000) × (1 + 15%) equals $621,000
Markup on direct cost only$615,000
Markup on the full cost$621,000
- Direct cost
- General conditions
- Markup
Price = Cost × (1 + Overhead) × (1 + Profit)
Adding the percentages (the mistake)
$800,000 × (1 + 8% + 10%) equals $944,000
Overhead first, then profit on top
$800,000 × (1 + 8%) × (1 + 10%) equals $950,400
Percentages added$944,000
Applied in sequence$950,400
- Cost
- Overhead
- Profit
In your books: The Contractor's Manual's estimating and financial chapters hold the break-even, markup and overhead definitions. The formulas themselves are not in any book on the desk.
Know these cold
The short list to have in your head on exam day. Every line is also a card in your flashcards.
- Crew-days
- Quantity ÷ daily crew output
- Break-even
- Fixed costs ÷ contribution margin (1 − variable cost ratio)
- Margin to price
- Price = cost ÷ (1 − margin)
- Markup on cost
- Cost × (1 + markup); 20% markup ≈ 16.7% margin
- Square-foot estimate
- Area × $/SF, order-of-magnitude only
- Equipment rate
- Ownership (depreciation, interest, insurance, taxes, storage) + operating (fuel, repairs)
- Unit labor cost
- Daily crew cost ÷ daily production (count every worker)
- Unit price
- Material + labor + equipment per unit of work
- Order quantity
- Net quantity × (1 + waste factor); 2,000 SF at 8% = 2,160 SF
- Labor burden
- FICA, unemployment tax, workers' comp, payroll-based liability, fringes on top of the wage
- General conditions
- Job overhead: superintendent, field office, temp power, dumpsters, security
- Home-office overhead
- Not a job cost; recovered through markup
- Allowance vs contingency
- Allowance = known item, undecided selection; contingency = reserve for the unknown
- Escalation
- Prices work at the cost level when it will be bought; not for prices already locked
- Quote leveling
- Add the cost of excluded scope to a quote before comparing it
- Compounded markup
- Cost × (1 + overhead) × (1 + profit), applied in sequence
- Estimate for a GMP
- Detailed takeoff from developed drawings, not a square-foot number
- Operating vs ownership
- Operating only when the machine works; ownership all year
Where it lives in your books
The real exam is open book. Knowing which book and which tab answer this topic is worth as much as memorizing it.
- Contractor's Manual · 8 recommended tabsThis is your home base on exam day. Learn its table of contents — most candidates lose time flipping because they never learned which chapter holds which statute.
- Walker's · 4 recommended tabsTakeoff questions reduce to unit discipline: convert everything to the unit being priced (CY, SF, LF) before doing arithmetic. The 27 cubic feet per cubic yard conversion is the most-used number in the book.
- Commercial Construction · 15 recommended tabsThis is the Project Management home book. Tab it by trade (site → concrete → masonry → steel → wood → envelope → finishes) so a question about a material sends your hand to one tab, not a table of contents.