Concrete & Masonry
15% of this examConcrete is tested as a process: forming and shoring, the mix (water-cement ratio, admixtures), placing and consolidating, reinforcing, testing, and curing. Masonry is tested as units plus mortar plus grout plus reinforcement, with bracing during construction and moisture control. Expect definitions, cause-and-effect scenarios, and quantity math (volumes in cubic yards, block counts, bar counts).
What the exam asks
- Concrete as a process: forms and shores, the mix, placing, reinforcing, testing and curing.
- Cause and effect: extra water, fast pours, free fall, missed curing and what each does to the finished work.
- Which test answers which question: slump, air, standard-cured and field-cured cylinders, 28-day breaks.
- Masonry as units, mortar, grout and reinforcement, with bracing and moisture control.
- Quantity math: cubic yards, bar counts, block counts and net wall area.
Part 1 of 5
Forms, shores and pressure
Forms are a temporary structure that carries a heavy liquid. Know what loads them, how fast the crew may fill them, and when they come out.
Forms and shores
Fresh concrete loads a form like a fluid: pressure rises with the rate of placement and the height still fluid, so the form design assumes a pour rate the crew must respect. Elevated slabs are reshored after stripping so construction loads spread through several floors. Forms come out only when the concrete has the strength the specifications or field-cured cylinders show.
Form pressure comes from pour rate
Fresh concrete pushes on a form like a heavy liquid until it starts to stiffen, up to a full fluid head of about 150 pounds per cubic foot times the depth. The faster the form fills, the more of its height is still liquid at once and the higher the pressure at the bottom. Ties, walers, and braces are designed for a stated placement rate and temperature. Pour faster than that and the form can blow out.
Pressure at the bottom = Unit weight × Depth of fluid concrete
Full fluid head pressure at the bottom, the most the form sees
150 lb per cu ft × 8 ft equals 1,200 lb per SF
In your books: Tab the formwork chapter of the Commercial Construction text.
Part 2 of 5
The mix, the pour and curing
Water, delivery timing, placing method and curing each have a cause-and-effect answer. Know what each mistake does to the finished concrete and what prevents it.
The mix and the pour
Strength and durability fall as the water-cement ratio rises; water added on site to loosen a load lowers the strength of the whole pour. Retarders buy time in hot weather, accelerators help in cold (calcium chloride is limited around rebar), air entrainment is for freeze-thaw and workability. Limit free fall to avoid segregation; vibrate vertically, into the lift below, and withdraw slowly. Cure by keeping moisture in (water, coverings, compound) for the specified period.
Cubic yards = Length × Width × Thickness (ft) ÷ 27. Order = Cubic yards × (1 + waste).
Volume in cubic feet
80 ft × 2 ft × 1.50 ft equals 240 cu ft
Volume in cubic yards
cubic feet ÷ 27 equals 8.89 CY
Order with waste
cubic yards × (1 + 10%) equals 9.8 CY
Water at the truck
Strength falls as the water-cement ratio rises. Water may be added on site only up to the amount the mix design held back at batching, noted on the ticket, and mixed in properly. If the load is still too stiff, the answer is a water-reducing admixture or an adjusted mix from the plant, not more water. Every addition is written on the delivery ticket.
Placing, vibrating, and cold joints
Limit free fall and use a tremie, drop chute, or pump hose so the stone does not separate from the paste. Insert the vibrator vertically at a spacing of about one and a half times its radius of action, down into the lift below, and pull it out slowly. Do not use the vibrator to move concrete sideways. A cold joint forms when fresh concrete lands against concrete that has started to set; prevent it with truck scheduling, a crew sized for the pour, and vibrating each lift into the last.
Curing and hot weather
Concrete gains strength only while it stays moist. Water curing, wet coverings, plastic sheeting, or a sprayed curing compound hold the moisture in, and specifications commonly call for at least seven days. Fans do the opposite. Hot, dry, windy weather pulls bleed water off the surface faster than it rises and tears the surface into plastic shrinkage cracks. The defenses: dampen the subgrade, cool the mix, fog spray, put up windbreaks, pour outside peak heat, and start curing right after finishing.
In your books: Tab the concrete chapter of the Commercial Construction text.
Part 3 of 5
Reinforcing steel
Bar size and grade are rolled into the bar, and laps and cover come from the drawings. Learn to read bar sizes, cover, laps and counts, and keep the steel where it was placed during the pour.
Reinforcing and testing
Bar number = eighths of an inch (#5 = 5/8 in). Cover protects steel: most against earth, least indoors. Laps are a multiple of bar diameter set by the engineer; chairs and bolsters hold position. Acceptance cylinders are sampled at intervals across the pour; slump checks workability; 28-day breaks verify f'c. Piles carry loads through weak soil to a pile cap under each column.
Diameter in inches = Bar number ÷ 8
Bar diameter
5 ÷ 8 equals 0.625 in
Rebar details
Bar size and grade are rolled into the bar: Grade 60 means 60,000 psi yield. Cover is greatest for concrete cast against earth, less for formed surfaces exposed to weather, least indoors. Lap length is on the structural drawings as a multiple of bar diameter, and bigger bars need longer laps. Field welding of rebar needs weldable steel and a qualified procedure. Chairs and bolsters keep the steel from being walked down during the pour.
Bars each way = (Length ÷ spacing, rounded up) + 1. Total length = Bars × bar length, both directions added.
Bars running the length (spaced across the width)
(30 ft × 12 ÷ 12 in) + 1 equals 31 bars
Bars running the width (spaced along the length)
(50 ft × 12 ÷ 12 in) + 1 equals 51 bars
Total linear feet of bar, no laps or waste
bars × 50 ft + bars × 30 ft equals 3,080 LF
In your books: Tab the reinforcing chapter of the Commercial Construction text. Its bar size table is one of the fastest lookups in the book. Placing Reinforcing Bars is a study reference for the cover rules. Learn them from it, but it stays home on exam day.
Part 4 of 5
Testing: what each test tells you
Slump, air and cylinders answer different questions. Match the test to the question and the distractors fall away.
Two sets of cylinders, two questions
Standard-cured cylinders are kept at controlled moisture and temperature. They tell you whether the mix as delivered meets the specification, and they are the basis of acceptance. Field-cured cylinders sit in the same conditions as the structure and tell you how strong the concrete in place is right now, which is the number that matters before stripping forms, pulling shores, or stressing tendons. Samples are taken at intervals across the pour, not all from one truck.
Slump, air, and strength are separate tests
Slump measures consistency and workability. Air content measures entrained and entrapped air. Cylinders broken in compression measure strength, verified at 28 days; a 7-day break usually runs about 65 to 75% of that, so a 4,000 psi mix should show roughly 2,800 psi at 7 days. If a load tests at 7 inches against a 3-to-5-inch window, one immediate check test on another part of the sample is allowed. If that fails too, the load does not go in the structure.
Expected 7-day strength = 28-day design strength × Percent expected
Healthy early indicator at 7 days
4,000 psi × 70% equals 2,800 psi
In your books: Design and Control of Concrete Mixtures is a study reference for the testing rules. Learn them from it, but it stays home on exam day.
Part 5 of 5
Masonry: mortar, grout and takeoff
Masonry is units plus mortar plus grout plus steel. Know the mortar types, what makes grout different, when walls need bracing, and how to count block.
Masonry
Mortar types rank M, S, N, O by strength (Type S for structural and below-grade work). Grout is high-slump so it fills the cells; high-lift grouting needs cleanouts at the base. Walls over 8 feet need bracing and a limited access zone until the roof or floor ties them in. Flashing and weep holes drain the cavity; blocked weeps send water into the framing. A standard 8×8×16 block covers 128 square inches, 1.125 blocks per square foot.
Masonry: mortar, grout, and takeoff
Mortar is stiff enough to carry the block; grout is fluid, commonly 8 to 11 inches of slump, so it fills the cells and bonds to the rebar. The mortar strength order is in the word MaSoNwOrK: M, S, N, O. Type N is the general-purpose mortar for above-grade veneer. Low-lift grouting in short pours needs no cleanouts; high-lift grouting does. For takeoff, net wall area = gross area − openings: a 100 × 12 ft wall with 160 SF of openings is 1,040 SF. Large openings are always deducted.
Net area = Gross area − Openings. Block = Net area × 1.125 per SF.
Gross area
100 ft × 12 ft equals 1,200 SF
Net wall area
gross − 160 SF equals 1,040 SF
Block before waste
net area × 1.125 equals 1,170 block
In your books: Mortar types sit in the tables of the Commercial Construction text. Masonry mortar, grout and bracing requirements are in the Florida Building Code, Building Ch. 21.
Know these cold
The short list to have in your head on exam day. Every line is also a card in your flashcards.
- Concrete volume
- L × W × thickness (ft) ÷ 27 = cubic yards; concrete ≈ 150 lb/cu ft
- Rebar size
- Bar number ÷ 8 = diameter in inches (#4 = 1/2, #5 = 5/8, #8 = 1)
- Cover against earth
- About 3 in (vs 3/4 in for interior slabs)
- Mortar strength order
- M > S > N > O
- CMU count
- 1.125 blocks per square foot of wall (8×16 face)
- Strength test
- Cylinders broken at 28 days verify specified f'c
- Form pressure
- Rises with placement rate; fluid head about 150 lb per cu ft × depth
- Reshores
- Carry construction loads down through two or more completed floors
- Standard-cured cylinders
- Acceptance of the mix as delivered
- Field-cured cylinders
- In-place strength for stripping forms and removing shores
- 7-day break
- About 65–75% of 28-day strength (4,000 psi → about 2,800 psi)
- Slump out of range
- One immediate check test; if it fails, reject the load
- Site-added water
- Only up to the amount held back on the ticket; record it
- Vibrator
- Vertical, into the lift below, about 1.5 × radius of action apart, slow withdrawal
- Curing
- Keep it moist; commonly at least 7 days
- Retarder / accelerator
- Retarder for hot weather; accelerator for cold
- Grout slump
- Commonly 8 to 11 in, so it flows into the cells
- Cleanouts
- Required at the base of the cells for high-lift grouting — FBC Ch. 21
- Masonry wall over 8 ft
- Braced, with a limited access zone, until tied in
- Rebar count
- (Length ÷ spacing) + 1 bars in each direction
Where it lives in your books
The real exam is open book. Knowing which book and which tab answer this topic is worth as much as memorizing it.
- Commercial Construction · 15 recommended tabsThis is the Project Management home book. Tab it by trade (site → concrete → masonry → steel → wood → envelope → finishes) so a question about a material sends your hand to one tab, not a table of contents.
- Concrete References · 4 recommended tabsTesting questions are definitional: slump = workability, cylinders at 28 days = strength, Proctor = compaction benchmark. Tab the test-methods chapter.
- Florida Building Code · 18 recommended tabsCode questions give themselves away with words like 'minimum', 'required', or 'permitted'. Go to the code — never answer a code question from memory when the book is on the desk.
Reading isn't learning. Retrieval is.
36 questions in this domain, each with an explanation and source.