Site Layout, Soils & Earthwork

17% of this exam

The first thing built on any site is the site. This domain covers how the building gets located (surveys, benchmarks, batter boards, setbacks and easements, flood elevations), what the ground under it is made of (soil types, the Proctor test, boring logs, water tables, foundation choice), and how it is moved and protected (cut and fill math, swell and shrinkage, sheeting and shoring, dewatering, erosion control, and material storage). The questions are a mix of definitions, plan reading, and arithmetic.

What the exam asks

  • Layout and plan reading: benchmark elevations, batter boards, squaring a corner, setbacks, easements and fill versus cut.
  • Soils and the soil report: which soils to keep, which to remove, SPT blow counts and what to do over weak layers.
  • Compaction: percent of Proctor maximum, lift thickness and the roller that fits the soil.
  • Earthwork arithmetic: swell, shrinkage, average end area, cubic yards and truck loads.
  • Water and site protection: wellpoints versus sumps, sheeting, silt fence, erosion control and stored material.

Part 1 of 5

Locating the building on the site

Everything on the job is measured from something fixed. This part covers the benchmark, the instruments, squaring corners and what the site plan says before the dozer moves.

Layout: datum, benchmark, and the 3-4-5

Every elevation on the project is measured from a benchmark of known elevation. Differential leveling is add the backsight, subtract the foresight: HI = benchmark + BS; point elevation = HI − FS. Batter boards sit outside the excavation so the building lines can be re-stretched after the stakes are gone. Corners are squared with a 3-4-5 triangle (or 6-8-10, 9-12-15) or by matching diagonals. Setbacks are measured from the property line; an easement stays clear of permanent structures.

Work it: Differential leveling

HI = Benchmark elevation + Backsight. Point elevation = HI − Foresight.

ft
ft
ft

Height of instrument (HI)

100 ft + 4.50 ft equals 104.50 ft

Elevation of the point (a larger rod reading means a lower point)

HI − 6 ft equals 98.50 ft

Which instrument does what

A total station measures angles and distance electronically and lays out coordinates as well as elevations. A builder's level and a laser level read elevations only. A measuring wheel gives a rough horizontal distance. GPS rovers tied to the project control do modern layout. A turning point is a temporary point used to carry a level run forward; a benchmark is the fixed point of known elevation everything is measured from.

Reading the site plan before the dozer moves

Contours show ground elevation. If the existing ground sits between the 24 and 26 contours and the finished floor is 27.50, the pad is a fill: 1.5 to 3.5 feet of it. Setbacks come off the property lines on every side they apply: a 100-foot-wide lot with 10-foot side setbacks leaves 80 feet of buildable width, and the front setback takes depth, not width. An easement lets a utility use and dig in a strip of land; the owner keeps title and cannot build a permanent structure on it.

Work it: Buildable width

Buildable width = Lot width − Side setbacks

ft
ft

Buildable width

100 ft − 10 ft − 10 ft equals 80 ft

Work it: Fill or cut from the contours

Fill depth = Finished floor − Existing ground. Below zero means a cut.

ft
ft
ft

Least fill (ground at the higher contour)

27.50 ft − 26 ft equals 1.5 ft

Most fill (ground at the lower contour)

27.50 ft − 24 ft equals 3.5 ft

In your books: Tab the Commercial Construction text at site work. Flood-resistant construction is in the Florida Building Code (Building §1612; Residential R322).

Part 2 of 5

What the ground is made of

The soil decides what you can build on and what has to come out. Learn which soils are good, which are bad and how the soil report tells you.

Soils: granular good, organic bad, Proctor decides

Well-graded sand and gravel drain and compact; clays shrink and swell; silts soften; organics (muck, peat) are removed. The Proctor test gives the maximum dry density and the optimum moisture; field density (nuclear gauge, sand cone) is reported as a percentage of that maximum, and the spec sets the percent (commonly 95–98). Fill goes in thin lifts because compaction effort fades with depth. Boring logs give SPT N-values: single digits mean loose or soft; deep foundations carry loads through weak layers to competent soil.

Proof-rolling and the soil report

Proof-rolling is a loaded dump truck or heavy roller driven over the exposed subgrade. Any spot that deflects, ruts, or pumps water is undercut and replaced before fill goes down. In the soil report, the SPT blow count is the number of hammer blows to drive the sampler 12 inches; single digits mean very loose sand or soft clay that will not carry ordinary footings, and the report will say to undercut and replace, densify, or bear below the weak zone. Fifteen feet of muck under a column means piles and pile caps, not wider footings.

In your books: Presumptive bearing values and footing depths are in the Florida Building Code (Building Ch. 18; Residential Ch. 4). OSHA's soil types and sloping angles (Subpart P, Appendices A and B) are tested here as well as in Safety, so one tab serves both.

Part 3 of 5

Compaction: test it, then build it right

Fill is only as good as its density test. This part covers how the test is figured and how lifts and rollers are chosen so the test passes.

Compaction testing, step by step

Percent compaction = field dry density ÷ Proctor maximum dry density. 110 ÷ 118 is 93%, short of a 95% spec, and the lift has to reach 112.1 pcf to pass. A near miss is still a miss: 94.9% fails a 95% spec and nobody rounds up. The fix is to adjust moisture toward optimum, re-roll, and retest before the next lift goes on. Fill placed too dry will not densify; too wet and it pumps.

Work it: Percent compaction

Percent compaction = Field dry density ÷ Proctor maximum dry density

pcf
pcf
%

Percent compaction

110 pcf ÷ 118 pcf equals 93.2%

Density the lift must reach to pass

95% × 118 pcf equals 112.1 pcf

Lifts and rollers

A roller's effort fades with depth. Put a lift down thicker than the machine can compact and the top passes while the bottom stays loose, and the slab settles later. Lift thickness is matched to the equipment, commonly on the order of 8 to 12 inches loose, and thinner for a hand plate compactor in a trench. Clay compacts by kneading, so it gets a sheepsfoot roller. Sand and gravel compact by vibration, so they get a vibratory roller or plate.

Part 4 of 5

Moving dirt: swell, shrinkage and haul math

Dirt changes volume as it is dug, hauled and placed. Know which state the question gives you, convert it, and always finish in cubic yards.

Earthwork arithmetic

Bank (in place) → loose (swelled) → compacted (shrunk). Loose yards = bank yards × (1 + swell); bank yards needed for a compacted fill = compacted ÷ (1 − shrinkage). Volumes come from the average end area method [(A1 + A2)/2 × L] or L × W × depth, always divided by 27 to reach cubic yards. Trucks are sized in loose yards; contracts pay in bank yards.

Work it: Bank to loose yards

Loose yards = Bank yards × (1 + Swell)

BCY
%

Loose yards to haul

1,200 BCY × (1 + swell) equals 1,500 LCY

Work it: Average end area

Volume = (A1 + A2) ÷ 2 × Length, then ÷ 27 for cubic yards

SF
SF
ft

Average end area

(60 SF + 90 SF) ÷ 2 equals 75 SF

Volume in cubic feet

average area × 200 ft equals 15,000 cu ft

Volume in cubic yards (stopping at cubic feet is the trap)

cubic feet ÷ 27 equals 556 CY

Haul math

Truck loads = loose cubic yards ÷ truck capacity in loose yards: 900 LCY in 12-yard trucks is 75 loads. If the question gives bank yards, swell them first (1,200 BCY × 1.25 = 1,500 LCY). For a compacted fill, work backward: a 150 × 100 × 2 ft pad is 30,000 cubic feet or 1,111 compacted yards, and at 10% shrinkage it takes 1,111 ÷ 0.90 ≈ 1,235 bank yards. Check the units the answer wants; cubic feet is the classic trap.

Work it: Bank yards for a compacted pad

Compacted yards = L × W × Depth ÷ 27. Bank yards = Compacted yards ÷ (1 − Shrinkage).

ft
ft
ft
%

Compacted volume in cubic feet

150 ft × 100 ft × 2 ft equals 30,000 cu ft

Compacted yards

cubic feet ÷ 27 equals 1,111 CCY

Bank yards needed

compacted yards ÷ (1 − shrinkage) equals 1,235 BCY

Work it: Truck loads

Truck loads = Loose yards ÷ Truck capacity in loose yards

LCY
LCY

Truck loads

900 LCY ÷ 12 LCY equals 75 loads

Trips to schedule (rounded up)

Round up equals 75 loads

In your books: The Commercial Construction glossary settles bank, loose and compacted. Tab it.

Part 5 of 5

Water, walls, erosion and stored material

Water and open cuts cause most of the trouble on a site. This part covers dewatering, shoring, the stormwater permit, the machines that do the work and how materials are stored.

Water, walls, and the stormwater permit

Design to the seasonal high water table, not the day of drilling. Dewater with sumps for small cuts, wellpoints for deep cuts in sand. Where a cut cannot be laid back near a structure, an engineered sheeting or shoring system supports it. The stormwater permit requires silt fence along the contour on the downslope side (toe trenched in), inlet protection, a stabilized rock entrance, temporary stabilization of idle areas, and tree barricades at the dripline.

Dewatering and the retention pond

Wellpoints are a line of small wells jetted into the ground around the excavation. They pull the water table below the bottom of the dig before digging, so the work is done in the dry and the soil does not boil or run. A sump pump handles water after it gets in, which is enough for small, shallow cuts. Pumping controls water, not soil; a cut next to someone else's footing still needs engineered sheeting or shoring. The retention pond is a requirement of the environmental resource permit: it holds the extra runoff that paving and roofs create.

Machines and stored material

An excavator digs below its own level and holds a narrow trench. A grader shapes and finishes. A scraper cuts, hauls, and spreads over long distances. A roller compacts. Stored material is a site-work question too: cement bags go up off the ground, covered and dry, and are used first in, first out. Gypsum board and lumber are kept out of the mud and the weather. The angle of repose is the slope a loose pile settles to on its own.

In your books: The Commercial Construction glossary settles the angle of repose definition.

Know these cold

The short list to have in your head on exam day. Every line is also a card in your flashcards.

Leveling
HI = BM + backsight; elevation = HI − foresight
Square corner
3-4-5 triangle (and multiples); equal diagonals
Cubic yard
27 cubic feet
Swell / shrinkage
LCY = BCY × (1 + swell); BCY = CCY ÷ (1 − shrink)
Percent compaction
Field dry density ÷ Proctor maximum dry density
Base flood elevation
The 1%-annual-chance (100-year) flood elevation on the FIRM
Total station
Angles and distance; lays out coordinates and elevations
Builder's or laser level
Elevations only
Larger rod reading
Means a lower point
Buildable width
Lot width minus both side setbacks (100 − 10 − 10 = 80 ft)
Easement
Right to use a strip; no permanent structures on it
Fill or cut
Finished grade above existing contours = fill; below = cut
Lift thickness
Commonly about 8 to 12 in loose; thinner for hand equipment
Sheepsfoot / vibratory
Sheepsfoot for clay (kneading); vibratory for sand and gravel
Proof-roll
Loaded truck over subgrade; undercut what deflects or pumps
SPT N-value
Blows to drive the sampler 12 in; single digits = loose or soft
Average end area
(A1 + A2) ÷ 2 × length, then ÷ 27 for cubic yards
Truck loads
Loose yards ÷ truck capacity in loose yards
Wellpoints vs sumps
Wellpoints lower the water table first; sumps pump what gets in
Tree barricade
At the dripline, to keep the root zone clear

Where it lives in your books

The real exam is open book. Knowing which book and which tab answer this topic is worth as much as memorizing it.

Reading isn't learning. Retrieval is.

42 questions in this domain, each with an explanation and source.