Scheduling & Jobsite Operations

13% of this exam

Content Area D of the outline: running the job once it is sold. CPM scheduling (forward and backward passes, float, lags, crashing, updates, look-aheads, time impact analysis), submittals and lead times, coordinating subcontractors (meetings, daily logs, manpower, RFIs, record drawings), cost control and earned value, inventory control, and sustainability programs such as LEED. The scheduling math must be done, not found.

What the exam asks

  • CPM arithmetic: forward and backward passes, the critical path, and total, free and negative float.
  • Lags, leads, crashing, updates and revisions, and how a delay is proved with a fragnet.
  • Working backward from a need date to an order date, and crew duration from labor-hours.
  • Earned value: CPI for cost, SPI for schedule, and forecasting from work in place.
  • Field records: daily reports, RFIs, meeting minutes and weather allowances.

Part 1 of 5

Reading the network: passes and float

The scheduling math on the exam must be done, not found. Start with the two passes, then learn what each kind of float tells you about a delay.

CPM in four moves

Forward pass gives early dates; backward pass gives late dates; total float = LS − ES (or LF − EF); the critical path is the longest path with zero float. Free float is delay without moving any successor. Lags add time between activities; leads overlap them. Crashing shortens critical activities by adding resources at a cost; fast-tracking overlaps phases and risks rework. A schedule update moves the data date and records progress; a revision changes logic. Negative float means the plan is late; a recovery schedule is the response.

Forward and backward pass at a merge

Forward pass: early finish = early start + duration, and where several activities feed one, the LATEST early finish of the predecessors sets its early start. Backward pass: late start = late finish − duration, and where an activity has several successors, the EARLIEST late start of the successors sets its late finish. Mixing those two rules up is the usual wrong answer.

Work it: Early finish and late start

Early finish = Early start + Duration. Late start = Late finish − Duration.

Day
Day
days

Early finish (forward pass)

Day 3 + 6 days equals Day 9

Late start (backward pass)

Day 10 − 6 days equals Day 4

Total float, free float, negative float

Total float = LS − ES = LF − EF: slip that does not move the project finish. Free float = successor's early start − this activity's early finish: slip that does not move any successor. Free float is figured from early dates only. Negative float means the plan cannot meet the required finish, and its size is the time to recover. Unless the contract assigns it, float belongs to the project: whoever needs it first uses it, and a delay absorbed by float earns no time extension.

Work it: Total float

Total float = Late start − Early start

Day
Day

Slip that does not move the project finish

Day 16 − Day 10 equals 6 days

Work it: Free float

Free float = Successor's early start − This activity's early finish

Day
Day

Slip that does not move any successor (early dates only)

Day 15 − Day 12 equals 3 days

Worked example

Fig — Forward pass: find the critical path
  1. Path A–B–D–F
    3 + 6 + 5 + 2 = 16 days
  2. Path A–C–E–F
    3 + 5 + 7 + 2 = 17 days
  3. Result
    Project duration 17 days; A–C–E–F is critical

    The other path carries 1 day of float.

In your books: The Contractor's Manual's project management chapter covers scheduling terms. Tab it, but practice the CPM arithmetic until the book is only a formula check.

Part 2 of 5

Relationships, crashing and proving a delay

Once the network is built, the questions turn to changing it. Know which tool shortens the job, which one only moves crews around, and how a delay gets proved.

Lags, leads, and relationship types

A lag is a required wait built into a relationship: three days of cure before stripping. A lead is a negative lag: the successor starts before the predecessor finishes. A start-to-start lag ties the successor's start to the predecessor's start, which is how follow-on trades are modeled (finishers start two days behind the hangers). Every activity except the start and finish milestones needs at least one predecessor and one successor; an open end gets false float all the way to the end of the job.

Crash the cheapest critical activity

Crashing adds labor, shifts, or equipment to shorten an activity. It only helps on the critical path: shortening an activity that has float just gives it more float. Among critical activities, pick the lowest cost per day saved first. Keep watching the other paths, because once a parallel path becomes critical too, both have to be shortened. Fast-tracking is different: it overlaps phases instead of adding resources. Resource leveling is different again: it uses float on non-critical work to smooth crew peaks without moving the finish.

Updates, revisions, and proving a delay

The baseline is the as-planned schedule accepted at the start. An update records actual starts, finishes, and remaining durations as of the data date and recalculates the forecast. A revision changes the plan for future work. To show the effect of a change or delay, a fragnet (a small network of the added activities) is inserted into the update that was current when the event happened; that is a time impact analysis. Milestones have no duration and use no resources.

Part 3 of 5

Ordering ahead and sizing crews

Long-lead items are ordered backward from the day you need them. Crew duration comes from labor-hours. Both are short calculations that are easy to get right once you know the steps.

Submittals, lead times, and look-aheads

Long-lead items are ordered backward from the need date: need date − lead time − review and approval time = order date. The submittal log tracks each item through the architect's review; the three-week look-ahead turns the master schedule into crew-level plans and exposes constraints (deliveries, inspections, access) before they bite.

Work it: Working backward to the order date

Order date = Need date − Lead time − Review and approval time

Week
weeks
weeks

Fabrication must start

Week 30 − 22 weeks equals Week 8

Submittal must start

Week 30 − 22 weeks − 6 weeks equals Week 2

Durations, manpower, and overtime

Duration = labor-hours ÷ (crew size × hours per day): 360 hours with five workers on eight-hour days is 9 working days. An area only holds so many workers before they get in each other's way, and stacking trades costs productivity and safety. Extended overtime also loses productivity week after week, so a 60-hour week produces far less than one and a half times a 40-hour week.

Work it: Crew duration

Duration = Labor-hours ÷ (Crew size × Hours per day)

hours
workers
hours

Crew hours per day

5 workers × 8 hours equals 40 hours

Working days

360 hours ÷ crew hours per day equals 9 days

In your books: Submittal review (A201 §3.10 to 3.12) is an AIA lookup. The Contractor's Manual covers submittal procedures.

Part 4 of 5

Coordination, records and weather

The daily report is the evidence behind any later claim. This part covers the meetings, records and field tools that keep trades building the same building.

Coordination and records

Pre-construction and weekly coordination meetings with distributed minutes, a daily report that records weather, manpower, deliveries, and delays (the evidence for any claim), RFIs that ask one clear question and get an answer that may become a change, record drawings kept current, and a manpower plan that staffs overlapping activities. Verbal directives are confirmed in writing. Inventory control protects stored materials and matches deliveries to the schedule.

Field coordination tools

Pull planning works backward from a milestone with the foremen who will do the work making the commitments. A preinstallation conference is held just before a high-risk scope such as roofing or waterproofing. Coordination drawings, now usually a combined BIM model with clash detection, sort out the above-ceiling space before installation. One shared set of control lines keeps every trade building the same building. When a sub falls behind, the order is: document the manpower in the daily reports, give written notice under the subcontract, get a recovery commitment.

Normal weather belongs in the baseline

Plan the weather you can expect for the place and season into the schedule, as non-work days in the calendars or as longer durations on weather-sensitive work. Then only weather unusually severe compared with that allowance supports a time extension.

In your books: The Contractor's Manual's project management chapter covers daily logs. Concealed conditions (A201 §3.7.4) are an AIA lookup.

Part 5 of 5

Cost control and earned value

Cost codes show an overrun while it can still be managed. Earned value turns cost and schedule into two indexes that each read below 1.0 as bad.

Cost control, earned value, and LEED

Cost codes compare budgeted to actual labor hours and quantities so overruns are seen while they can still be managed, and feed the next estimate. CPI = earned value ÷ actual cost (below 1.0 is over budget); SPI = earned value ÷ planned value. LEED (USGBC) certifies buildings as Certified, Silver, Gold, or Platinum by points across credit categories; Green Globes is the alternative rating system the outline names.

Earned value and forecasting

CPI = earned value ÷ actual cost; SPI = earned value ÷ planned value. Below 1.0 is bad on either one, and they answer different questions: CPI is cost, SPI is schedule. $200,000 earned for $250,000 spent is a CPI of 0.80. Forecast from work in place, not from hours burned: 600 hours for 50% of the work projects to 1,200 hours against a 1,000-hour budget. When the unit cost matches the estimate but more units were used, the overrun is quantity: takeoff, waste, or rework.

Work it: Cost performance index

CPI = Earned value ÷ Actual cost

$
$

CPI (below 1.0 is over budget)

$200,000 ÷ $250,000 equals 0.80

Work it: Schedule performance index

SPI = Earned value ÷ Planned value

$
$

SPI (below 1.0 is behind schedule)

$270,000 ÷ $300,000 equals 0.90

Work it: Forecast from work in place

Forecast hours = Hours to date ÷ Percent complete

hours
%
hours

Forecast hours at completion

600 hours ÷ percent complete equals 1,200 hours

Over (+) or under (−) budget

forecast − 1,000 hours equals 200 hours

In your books: Sustainability questions are definitional (LEED levels, Green Globes). That is memory, not lookup.

Know these cold

The short list to have in your head on exam day. Every line is also a card in your flashcards.

Total float
LS − ES = LF − EF; zero on the critical path
Critical path
Longest path through the network = minimum project duration
Order date
Need date − lead time − submittal review time
CPI
Earned value ÷ actual cost (< 1.0 = over budget)
Crew duration
Labor-hours ÷ (crew size × hours per day)
LEED levels
Certified, Silver, Gold, Platinum (points-based)
Early finish
ES + duration; at a merge the latest predecessor EF governs
Late start
LF − duration; with several successors the earliest LS governs
Free float
Successor's ES − this activity's EF
Negative float
Forecast finish is later than required; the amount is the time to recover
Float ownership
Belongs to the project unless the contract says otherwise
Lag / lead
Lag = required wait; lead = overlap (negative lag)
Crashing order
Critical activities only, lowest cost per day first
Resource leveling
Uses float to smooth manpower; finish date unchanged
Data date
Divides actual history from the remaining plan in an update
Fragnet
Inserted into the update current at the time of the delay (time impact analysis)
SPI
Earned value ÷ planned value (< 1.0 = behind schedule)
Forecast at completion
Hours to date ÷ percent complete
Bar chart limit
Shows no logic ties, so no float or critical path
Milestone
Zero duration, no resources

Where it lives in your books

The real exam is open book. Knowing which book and which tab answer this topic is worth as much as memorizing it.